Risk Assessments

Risk Assessments are separated into four distinct areas:

  1. Campus - meaning the university campus where the ANGLO centre is based
  2. Activities - meaning social activities that form the activity or social programme (e.g. sports, discos, karaoke)
  3. Excursions - meaning trips the students take
  4. Academic - meaning workshops, classes and exams

Risk Assessments for each area have two parts, part A and part B

Part A:

  • is completed in a general way before the staff arrive at centre
  • is updated to be specific to each centre by the SWO/WTS/AM/PM on arrival at centre, before students arrive
  • is reviewed by Head Office staff in conjunction with the SWO/WTS/AM/PM before students arrive
  • is communicated to centre staff

Part B:

  • is completed by the SWO/WTS/AM/PM on a regular basis i.e. prior to each session to identify new and current risks relevant to each session
  • is communicated to the relevant staff at the meeting point/team meeting and via WhatsApp
  • is then communicated to GLs and students by the relevant staff
Risk Assessment Documents

ANGLO's Risk Assessment documents are Google Sheets, accessible by all managers at each centre. Each centre has 5 documents:

  1. Campus Part A
  2. Activities Part A
  3. Excursions Part A
  4. Academic Part A
    and finally
  5. Risk Log - this is the Part B document that is regularly updated and is considered a 'live' log of all risks in all areas of the centre's operations

The Risk Log document feeds all recorded risks back to the relevant Part A document to maintain clean records e.g. a risk in the Risk Log categorised as 'Academic', can be viewed in the Academic Part A document.
This approach means that there is only one document requiring regular updates.

Assessing Risks

ANGLO uses the following risk calculation:

Likelihood x Severity = Risk Rating

Likelihood and Severity are assessed on a scale of 1 to 3 (low to high) giving a Risk Rating of 1 to 9 (low to high). Low: 1-3, Medium: 4-6, High: 7-9

Risk Ratings that come out as High (7 to 9) must be reported to the Head Office team. This should happen automatically via the Risk Log document, but advice can always be sought from [email protected]